Construction Schedule 2021

Ensuring the Macdonald and MacKay bridges remain safe for the traveling public requires significant investment and ongoing capital projects. What follows is a list of projects taking place that will require full bridge closures for the summer and fall 2021. The closures are tentative. The work is weather dependent.

Bridge Project Full bridge closure time (all dates are tentative)
MacKay Bridge Resurfacing  two north lanes and Dartmouth approach spans 7:00pm Friday, July 16 – 5:30am Monday, July 19
MacKay Bridge Resurfacing  two north lanes and Dartmouth approach spans 7:00pm Friday, July 23 – 5:30am Monday, July 26
MacKay Bridge Replacing expansion joint 7:00pm Friday, August 6 – 5:30am Monday, August 9
MacKay Bridge Replacing expansion joint 7:00pm Friday, August 13 – 5:30am Monday, August 16
MacKay Bridge Replacing expansion joint on Dartmouth approach 7:00pm Friday, August 20 – 5:30am Monday, August 23
MacKay Bridge Replacing expansion joint on Dartmouth approach 7:00pm Friday, September 3 – 5:30am Monday, September 6
MacKay Bridge Replacing expansion joint on Dartmouth approach 7:00pm Friday, September 10 – 5:30am Monday, September 13
Macdonald Bridge Replacing bearing on approach span 7:00pm Friday, October 15 – 5:30am Monday, October 18
Macdonald Bridge Pier rehabilitation and bearing replacement 7:00pm Friday, October 22 – 5:30am Monday, October 25

 

 