2018 closures

Updated September 8, 2018. Continuous overnight closures are complete for the Big Lift. Periodic daytime lane closures and overnight closures will be required until the end of 2018 and will be communicated in advance. The closures are required to complete the Big Lift. Another project not related to the Big Lift, replacing bearings on several approach spans, also requires several closures and will be noted in the closures schedule below.

Closures to the Macdonald Bridge

Date

 

Time

Saturday, October 13 6am – 9pm (sidewalk and bike lane also closed – shuttle service provided)
Sunday, October 14 6am – 9pm (sidewalk and bike lane also closed – shuttle service provided)